Pipeline, facility and infrastructure notices and reports

Amendments to the petroleum and gas reporting guideline were released on 31 October 2018. Find out more about the new reporting requirements.

You must notify us before you construct, commission or operate a licensed petroleum pipeline. You must also submit an annual report for the petroleum pipeline and for any other licensed petroleum facility.

Holders of petroleum leases who have constructed infrastructure associated with development (e.g. gathering lines, compressor stations, water treatment facilities) must provide information on these items.

Read how to meet your notification and reporting obligations under Queensland resources legislation, and download a flowchart of reporting requirements for petroleum pipeline licences (PDF, 129KB).

Permits this applies to

  • Petroleum lease
  • Petroleum pipeline licence
  • Petroleum facility licence

Before starting activities

Check requirements for land access and other notices before starting petroleum and gas activities.

How to lodge your notices and reports

The tables below show what you need to submit and how to do it. If you need more help:

Submit your commissioning or decommissioning report online.

Submit report

Petroleum pipeline licence

Report/notice and legislation When to lodge How to lodge
Notice of application to relevant local government
(P&G Act1 s. 409A)
Within 10 business days after making the application Submit a copy of the application (minus the capability criteria) to each relevant local government authority
Public notice requirement
(P&G Act s. 411)
Before the grant of the licence, publish the public notice with a submission period of at least 30 business days Publish a public notice in a newspaper circulating throughout the state or, for an area pipeline licence, generally in the area
Notice to chief inspector before pipeline construction starts
(P&G Act s. 419A)
At least 20 days before construction starts Email notice to Chief Inspector Petroleum and Gas at gassafe@dnrme.qld.gov.au
Notice of completion of pipeline
(P&G Act s. 420)
Point-to-point pipeline licence: within 6 months after completion
Area pipeline licence: within 40 business days after completion
Submit notice with fee by post to Petroleum Assessment Hub, Attn Petroleum Registrar
Notice to chief inspector before operating plant is commissioned or operated
(P&G Act s. 673A)
Within 20 business days before the commission or operation of the plant Email notice to Chief Inspector Petroleum and Gas at gassafe@dnrme.qld.gov.au
Notice to public road authority of pipeline constructed on public road
(P&G Act s. 421)
Within 6 months after completion Submit to public road authority
Annual report for a petroleum facility licence or pipeline licence
(P&G Act s. 552,(General Regs2 s. 13)
Within 2 months after licence anniversary

Upload report to QDEX Reports. For large digital data (excluding .txt and .csv files), post to:

QDEX Support
Statewide Operations
Department of Natural Resources, Mines and Energy
PO Box 15216
CITY EAST QLD 4002

1P&G Act: Petroleum and Gas (Production and Safety) Act 2004
2General Regs: Petroleum and Gas (General Provisions) Regulation 2017

Petroleum lease

Report/notice and legislation When to lodge How to lodge
Infrastructure report for petroleum lease
(P&G Act1 s. 552B)
On or before 1 September each year

Upload report to QDEX Reports. For large digital data (excluding .txt and .csv files), post to:

QDEX Support
Statewide Operations
Department of Natural Resources, Mines and Energy
PO Box 15216
CITY EAST QLD 4002

1P&G Act: Petroleum and Gas (Production and Safety) Act 2004

Petroleum facility licence

Report/notice and legislation When to lodge How to lodge
Notice of application to relevant local government
(P&G Act1 s. 445A)
Within 10 business days after making the application Submit a copy of the application (minus the capability criteria) to each relevant local government authority
Annual report for a petroleum facility licence or pipeline licence
(P&G Act s. 552, General Regs2 s. 13)
Within 2 months after licence anniversary

Upload report to QDEX Reports. For large digital data (excluding .txt and .csv files), post to:

QDEX Support
Statewide Operations
Department of Natural Resources, Mines and Energy
PO Box 15216
CITY EAST QLD 4002

1P&G Act: Petroleum and Gas (Production and Safety) Act 2004
2General Regs: Petroleum and Gas (General Provisions) Regulation 2017